Commute's New Dawn

The opening of the new Woodrow Wilson Bridge tops off two difficult decades of community debate, Congressional-wrangling, consultant studies and blue-collar construction that many times seemed to be in serious trouble, before turning into a mega-project success story.
The opening of the new Woodrow Wilson Bridge tops off two difficult decades of community debate, Congressional-wrangling, consultant studies and blue-collar construction that many times seemed to be in serious trouble, before turning into a mega-project success story.
Discussion Policy
Comments that include profanity or personal attacks or other inappropriate comments or material will be removed from the site. Additionally, entries that are unsigned or contain "signatures" by someone other than the actual author will be removed. Finally, we will take steps to block users who violate any of our posting standards, terms of use or privacy policies or any other policies governing this site. Please review the full rules governing commentaries and discussions. You are fully responsible for the content that you post.

Once all that was settled, there was still the matter of paying for it. The states wanted the federal government to pay for most of the bridge, which was the only portion of the nation's interstate system still federally owned. Congress agreed to pay $900 million, but that left a $600 million gap over what the states were contributing. And that was before the price tag jumped by half a billion dollars, bringing the total to about $2.5 billion.

Finally, a concerted effort by several local congressmen, led by Sen. John W. Warner (R-Va.), persuaded Congress to raise its contribution to $1.5 billion for what has become a $2.44 billion project.

Money did not beget happiness -- or even a workable state of harmony. Virginia, led by Republican Gov. James S. Gilmore III, and Maryland, led by Democratic Gov. Parris N. Glendening, were at odds on practically every issue.

"At the beginning, we couldn't even agree on whether to build this thing in feet or meters," said Jim Ruddell, construction manager for the bridge. He wasn't kidding. It took a few meetings and a couple of months to solve that one, Ruddell said.

Agreeing on which state would manage which part of the project, noise regulations and whether to hire unionized workers were just a few of the other sticky issues.

The sides came up with an innovative solution for their loveless marriage: They sought counseling. Specifically, they created a 13-member committee that included federal, state and local officials and was charged with resolving many of the disputes.

"That was the real breakthrough in terms of being able to reach agreement on the process," Maryland State Highway Administrator Neil J. Pedersen said.

But serious problems continued to dog the effort. A big meeting to discuss the contract for construction of the bridge was interrupted by the terrorist attacks on Sept. 11, 2001.

Three months later, before about 300 people in what was supposed to be a celebration, project officials unveiled the bids. There was just one, and it was nearly $400 million over budget.

"You could have heard a pin drop," Ruddell said. "At first we all thought we incorrectly heard the bid or transposed the numbers or something. But there it was."

Project managers didn't know what to do. Had they grossly underestimated costs? Was the contractor trying to take advantage of them? Had prices escalated after the terrorist attacks?

After months of deliberation, they decided to split the construction work into three contracts. Although the project was delayed by 14 months, they eventually made deals at the prices they wanted.

That was the turning point. Contractors have hit their targets, and the working agreement has been held up as a model at a time when many major public works projects have foundered. The now infamous "Big Dig," which put a major Boston highway underground, was estimated at $2.6 billion but cost $14.6 billion. Replacement of the San Francisco-Oakland Bay Bridge is mired in delays, and the cost has risen from $2.6 billion to $5.5 billion.

Although Thursday's ceremony marks the completion of the first of the two spans, the bridge isn't scheduled to open to traffic until June 9, when the Beltway's outer loop is rerouted onto it. A month later, inner loop traffic will go onto it and the old bridge, which opened in 1961, will come down.

Traffic will run both ways on the six-lane span until summer 2008, when it will become part of the outer loop and the second six-lane span will open as the inner loop.

On shore, the 7.5-mile project includes the revamping of two interchanges on both sides of the river and the widening of the Beltway to match the bridge. The bulk of that work will be done when the second span opens, but it won't be completed until 2011.

The bridge that is being replaced is a traffic killer. It's not wide enough to handle the road around it, and the drawbridge opens five times a week. Because the bridge has no shoulders, traffic comes to an immediate and prolonged halt when there's as much as a fender bender -- and there always seems to be a fender bender.

Both spans of the new bridge will have shoulders on each sides. The lanes on each span will be divided into two sets of three, one set for local drivers and the other for express traffic. One of the local lanes will connect to access ramps for the heavily used exits on both sides of the bridge. A pedestrian path will be included.

The transit lanes, which are in the express sections, will probably not open when the spans are finished. Maryland and Virginia are studying the addition of express toll lanes, which would allow for bus service. Other considerations include a Metro extension or light rail.

The opening of the first span won't increase the number of lanes over the old bridge, but its shoulders will allow accidents to be cleared in relatively short order, and its smooth surface will ease drives. In addition, its height will reduce the number of times it is opened each year from 260 to 60.

When the second span opens, the bridge will eliminate the bottleneck the old six-lane bridge causes on the eight-lane Beltway. Traffic experts expect the daily jams to all but disappear, at least in the short term, before the increased capacity begets more development.

"Instead of being a regional bottleneck, it will be a transportation facility that will actually make it easier to get between two states and literally bring the region together," Porcari said.

The bridge also should help alleviate some of the increasingly long tie-ups on such alternate routes as the 14th Street Bridge, the American Legion Bridge and the Harry W. Nice Memorial Bridge in Southern Maryland.

"This ranks up there with the 1970s when the steel plates and trenches in downtown D.C. were removed with the opening of the Metrorail system," said Virginia Transportation Secretary Pierce R. Homer. "The region suffered through a decade of inconvenience, and those investments paid off handsomely, just as they've suffered now and these investments are paying off."


<       2


More in the Maryland Section

Blog: Maryland Moment

Blog: Md. Politics

Washington Post staff writers provide breaking news coverage of your county and state government.

Local Explorer

Local Explorer

Use Local Explorer to learn about Washington, D.C., Maryland and Virginia communities.

Md. Congressional Primary

Election Results

Obama and McCain swept the region on February 12.

FOLLOW METRO ON:
Facebook Twitter RSS
|
GET LOCAL ALERTS:
© 2006 The Washington Post Company