At 8 p.m. Friday, crews on the Wilson Bridge start construction that will switch the inner loop of the Capital Beltway onto the new bridge. Southbound traffic will merge into one lane through Monday while construction crews mill and pave connections from the Beltway to the new bridge. Rerouting the inner loop is the latter of two traffic shifts; the outer loop switch occurred last month. All six lanes will be open on the new bridge after this weekend.

When: From 8 p.m. Friday to as late as 5 a.m. Monday.
Where: I-95 South from the Route 210 interchange in Maryland to the Route 1 interchange in Virginia.
What: The three inner loop lanes will be reduced to a single lane approaching the bridge in Maryland to shift traffic to the new span. Three ramps will be closed and detoured. Delays and traffic backups are expected to be worse this weekend than during the outer loop switch last month.
Monday: All ramps are scheduled to reopen by 5 a.m., and all six lanes of I-95/I-495 will be open on the new bridge.

Second Switch Begins Friday Night

Discussion Policy
Comments that include profanity or personal attacks or other inappropriate comments or material will be removed from the site. Additionally, entries that are unsigned or contain "signatures" by someone other than the actual author will be removed. Finally, we will take steps to block users who violate any of our posting standards, terms of use or privacy policies or any other policies governing this site. Please review the full rules governing commentaries and discussions. You are fully responsible for the content that you post.
© 2006 The Washington Post