[an error occurred while processing this directive]

This order, issued by Judge Kaye Christian, explains which D.C. public schools may open late for the 1997 school year because of fire code violations.

Jump to the schools that are:

  • Cleared to open
  • Cleared pending inspection
  • Scheduled for repairs by 8/15
  • Scheduled for repairs by 8/31
  • Scheduled for repairs by 9/20


    Go to Schools Crisis Page

    Go to Washington World Section

    Go to Home Page
    Spacer

  • Spacer

    Fire Code Violations Order

    Judge Kaye Christian
    Unedited Material
    July 11, 1997

    SUPERIOR COURT OF THE DISTRICT OF COLUMBIA CIVIL DIVISION

    PARENTS UNITED FOR THE DISTRICT OF COLUMBIA SCHOOLS, et al., Plaintiffs,

    v.

    MAYOR MARION S. BARRY, et al., Defendants.

    Civil Action No. 92-3478
    Judge Kaye K. Christian

    O R D E R

    On July 10, 1997, this Court commenced hearings in the instant matter to further address the defendants compliance with the Court's Order of June 10, 1994, and subsequent orders. At the conclusion of these hearings on July 10, 1997, this Court cleared one hundred and seven (107) schools to open at the start of the school year on September 2, 1997. Fifty (50) schools have not been cleared to open as of this date. (This number is comprised mainly of schools which are scheduled to have new roofs replaced and installed.)

    As mentioned by this Court on previous occasions, this Court's Order of June 10, 1994, is the touchstone of all subsequent Orders issued by this Court which continue to require the active enforcement of the Fire Code. Since the issuance of the June 10, 1994 Order, this Court has issued over fifty (50) Orders reiterating the June 10, 1994 Order. The-Court's Order of June 10, 1994, sets forth the requirements of the District of Columbia Fire Prevention Code ["Fire Code"] and the responsibilities of the code enforcement officer, the Fire Chief.

    Therefore, since June 10, 1994, a period of over three years, defendants have been under a continuing Order to abate any and all Fire Code violations in District of Columbia Public Schools. This Court's Order has remained the same -- Fire Code violations must be abated.

    Consistent with previous practice, the Court has conducted a series of prehearing conferences. These pre-hearing conferences have provided an efficient forum for all parties to address Defendants' compliance with the Court's Order of June 10, 1994, and subsequent Orders. These conferences have permitted the Court, with the assistance of Plaintiffs' and Defendants' counsel, to review the progress of Fire Code abatement on a school by school basis, and to identify and narrow the remaining issues for resolution during the in-court hearing.

    In this regard, the Court's review during the pre-hearing conference and incourt hearing is based on the following factors: the Fire Inspection Reports and Fire System Operations Reports; contractors' reports detailing and confirming corrective work performed; the certification of the Fire Chief that the schools are free of Fire Code violations and the certification of the Fire Marshal that all fire alarm systems and the back-up thereto are tested and found operational; that sprinklers are free of paint and functional; that all fire drill records are in proper order; and that all fire doors are operational and are not locked or blocked.

    The Court held pre-hearing conferences on July 1, 1997, July 2, 1997, July 3, 1997, July 7, 1997, July 8, 1997 and July 9, 1997. (The Court in its Order of February 27, 1997 scheduled the in-court hearing for July 10, 1997.) As a result of the prehearing conferences and the in-court hearing on July 10, 1997, and based on Defendants' submissions and the report of the Fire Chief for the District of Columbia, the Court finds the following schools free of Fire Code violations and cleared for opening:

    Elementary Junior High Middle Senior High
    Amidon Eliot BackusBallou
    Bancroft Evans Garnet Patterson Banneker
    Bowen Hamilton Roper Coolidge
    Brent Hart SousaD.C. Street Academy
    Brightwood Hine Lincoln Duke Ellington
    Brookland Johnson School w/o Walls
    Burroughs Kramer Penn Center
    Carver Langley Woodson H. D.
    Clark Paul Eastern
    Cooke H. D. Douglass
    Davis Shaw
    Draper Taft
    Drew Terrell R. H.
    Eaton Rosario
    Emery
    Ferebee-Hope
    Ft. Lincoln
    Garrison
    Gibbs
    Golding
    Giddings
    Harris C. W.
    Harris P. R.
    Hearst
    Hendley
    Janney
    Kenilworth
    Ketchum
    Key
    Kimball
    MLK, Jr.
    Langdon
    LaSalle
    Leckie
    Logan
    McGogney
    Malcolm X
    Mann
    Miner
    Monegomery
    Moten
    Murch
    Noyes
    Oyster
    Patterson
    Payne
    Peabody
    Plummer
    Powell
    Raymond
    Reed
    River Terrace
    Ross
    Rudolph
    Savoy
    Seaton
    Shepherd
    Simon
    Slowe
    Smothers
    Stanton
    Steven
    Stoddert
    Takoma
    Terrell M. C.
    Thomas
    Thomson
    Tubman
    Turner
    Van Ness
    Walker-Jones
    Watkins
    Weatherless
    Webb
    West
    Wheatley
    Whittier
    Wilson J. O.
    Wilkinson

    The Following schools have been closed by the District of Columbia Public Schools and are therefore not a part of this review process:

    Closed Schools
    Armstrong Adult Education Center
    Blow Elementary
    Burdick Senior High
    Chamberlain Senior High
    Filmore Elementary Arts Center
    Hardy Middle
    Harrison Elementary
    Keene Elementary
    Lewis Elementary
    McKinley
    Miller Junior High
    Petworth Elementary
    Richardson Elementary
    Woodbridge Elementary
    Old Congress Heights Elementary
    Lenox
    Taft Junior High
    Douglass Junior High

    The Defendants have requested that Burdick, Taft and Douglass although closed, be considered in this review hearing because these schools will be used as "swing" facilities or alternative sites.

    The Court notes that two schools have had new roofs replaced by the District of Columbia Public Schools. However, these schools have not yet had the required re-inspection by the Fire Department and reports have not been submitted to the Court. Therefore, these two schools are not cleared to open. These schools are:

    Elementary
    Houston
    Meyer

    During the pre-conference hearing on July 9, 1997 and the in-court hearing on July 10, 1997, General Williams of the District of Columbia Public Schools testified that a number of the schools are presently scheduled for complete or partial roof replacements. General Williams advised the Court that the roof replacement work would be completed at three different time periods. The completion dates are August 15, 1997, August 31, 1997, and September 20, 1997. It is noted that as soon as each new roof is installed, the Fire Department is required to inspect the school and submit fire inspection reports regarding its findings.

    The following schools are scheduled to have roofs completely or partially replaced by August 15, 1997, after which an inspection must be conducted by the Fire Department:

    Elementary
    Shadd
    Tyler
    Merritt

    * Sharpe Health, a special education school, has roof repairs scheduled for completion on August 15, 1997.

    The following schools are scheduled to have their roofs completely or partially replaced by August 31, 1997, after which an inspection must be conducted by the Fire Department:

    Elementary Junior High Middle Senior High
    Adams Deal Stuart-Hobson Anacostia
    Birney Jefferson Spingarn
    Burrville MacFarland Roosevelt
    Gage-Eckington Washington
    Garfield Wilson, W.
    Lafayette
    Lee, Mamie D
    Nalle
    Maury
    Monroe
    Orr
    Randle Highlands
    Young
    Benning

    The following schools are scheduled to have their roofs completely or partially replaced by September 20, 1997, after which an inspection must be conducted by the Fire Department:

    Elementary Junior High Senior High
    Aiton Browne Bell Multicultural
    Barnard Francis Cardozo
    Beers Dunbar
    Bunker Hill Phelps
    Cleveland
    Cook J. F.
    Fletcher-Johnson
    Green
    Hyde
    Ludlow-Taylor
    Park View
    Shadd
    Truesdell
    Winston

    The Court expressed support for the installation of new roofs. The Court was surprised, however, to learn that some roof installations would not be complete until August 31, 1997, and others as late as September 20, 1997. The Court expressed dismay at this schedule for completion, which when taken into consideration with the fact that each school must be inspected by the Fire Department after the roof installations, places the date for occupancy by students and staff even later than that projected.

    The Court was advised that as many as fourteen (14) contracting companies would be working on the installation of the roofs and that these contractors were prequalified for the job. Based thereon, the Court inquired why the work could not be completed before the opening of school. The Court expressed concern that the roof replacements and installations would not be complete in order for the schools to open on time. The Court was particularly concerned with those schools whose roofs are scheduled to be replaced by August 31, 1997 and September 20, 1997, considering that District of Columbia Public Schools are scheduled to reopen on September 2, 1997.

    The Court noted that the roofing schedule was very tight. Such a schedule puts Defendants in the likely position of not having the schools ready for opening. Further, the Court reminded Defendants that last August was one of the rainiest ever. Inclement weather delayed many roof repairs in August 1996.

    The Court also inquired of Defendants as to whether they had devised a plan to house students and staffs in the event that the schools are not ready on September 2, 1997. Defendants requested that the Court allow occupancy of the school buildings while the roofs are being replaced. The Court pointed out that it has never in the history of the case allowed any school building to be occupied while the roof was being repaired. The simple reason for this is that a breach in the roof constitutes a Fire Code violation. The Court notes that it has certainly been consistent in this regard with respect to Tyler Elementary, Noyes Elementary, Sharpe Health, Brightwood Elementary, Jefferson Junior High and Deal Junior High.

    The Court also notes that more recently, the Fire Department exercised its legitimate authority in enforcing the Fire Code by closing Roosevelt Senior High, Bell Mutlicutural and Shaw Junior High. In April 1997, during the course of an inspection of Shaw Junior High, Inspector Timothy A. Cropps, properly exercising his enforcement authority, evacuated and closed Shaw Junior High School because of a breach in the roof. This school remained closed until the roof repair work and other repairs were completed, and the school was later re-inspected and cleared of Fire Code violations by the Fire Department. The same was true for Roosevelt Senior High and Bell Multicultural Center. These schools were evacuated and closed by the Fire Department due to a breach in the roof. Students and staff were not permitted to reenter the buildings until the breach in the roofs were repaired. It stands to reason therefore, that while the roofs are being replaced the Fire Department has every authority to close the schools if they are occupied by students and staff.

    The Court is in no way suggesting how many roofs should be replaced and when the work is to be done. The Court is requiring, however, that if such work is undertaken it should be completed prior to the reopening of school. This is not an unreasonable expectation. Defendants knew, or should have known, which schools needed new roofs and how long it would take to replace these roofs given the September 2, 1997, date which Defendants set for the reopening of schools. Certainly Defendants could not expect to install new roofs while the school buildings are occupied by students and staff. This has never occurred under the mandate of this Court. It seems clear to the Court, therefore, that based on the September 2, 1997, school reopening date, the number of roofs repaired and the timing of such repairs after September 2, 1997, will depend on the ability of the school system to absorb students and staff that are displaced. This Court has never sanctioned the occurrence of any roof repairs while school buildings are occupied by students and staff.

    Plaintiffs' position was not clear to the Court from the record in this hearing. The Court notes that Plaintiffs stated in Court on July 10, 1997 that: "We are not advocating that the schools be passed that are having new roof work." However, Plaintiffs requested that the Court make itself available to monitor the situation while the repairs are in progress. This Court has always made itself available throughout these proceedings to receive motions and schedule hearings. This review process will be no different from others that have taken place. The Court will schedule weekly hearings on Thursdays at 12:00 noon in Courtroom 215, unless otherwise advised by the Court, to review the progress Defendants are making in replacing and installing the new roofs. If lead counsel for Defendant or Plaintiff is unavailable on any of these scheduled hearings, the Court will accept substitute counsel.

    The Court admonishes Defendants to begin devising plans for alternative sites for students and staff from those schools which will not be ready for September 2, 1997. These plans shall be filed with the Court and served on Plaintiffs by August 18, 1997.

    Wherefore, it is this 11th date of July, 1997, hereby

    ORDERED, that the Court will hold a scheduled hearing on the above-captioned matter every Thursday at 12:00 noon in Courtroom 215, unless otherwise advised by the Court; and it is further

    ORDERED, that the first such hearing shall occur on July 17, 1997; and it is further

    ORDERED, that any school with outstanding Fire Code violations will not be cleared for use; and it is further

    ORDERED, that Defendants shall devise and file with this Court and serve on Plaintiffs by August 18, 1997, a plan setting out alternative reporting sites for those schools they anticipate will not be free of Fire Code violations by September 2, 1997; and it is further

    ORDERED, that Defendants shall complete the abatement of all remaining Fire Code violations in any school not cleared for opening prior to submitting any petitions to this Court; and it is further

    ORDERED, that any petition submitted must be supported by affidavits and detailed documents evidencing all corrective work completed on the schools not cleared for opening; and it is further

    ORDERED, that the Court's Order of June 10, 1994, and subsequent Orders remain in full force and effect.

    SO ORDERED.

    KAYE CHRISTIAN
    Kaye Christian
    Associate Judge
    (Signed in Chambers)

    Copies to:

    Barbara Kagan, Esq.
    Andrea Evans, Esq.
    Mary Levy, Esq.
    STEPTOE & JOHNSON
    1330 Connecticut Avenue, N.W.
    Washington, DC 20036

    Pastell Vann, Assistant Corporation Counsel
    Brenda Walls, Assistant Corporation Counsel
    OFFICE OF THE CORPORATION COUNSEL
    441 4th Street, N.W.
    Washington, DC 20001

    Back to the top

    Spacer

    WashingtonPost.com
    Navigation image map
    [an error occurred while processing this directive]
    Home page Site Index Search Help! Home page Site Index Search Help!